Weekly Construction Activity Update

Hotel (Terrace Bridge Level) – Concrete will be poured in front of the hotel at the Terrace Bridge Level. Hotel…

Weekly Construction Activity Update

Hotel (Terrace Bridge Level) - Concrete will be poured in front of the hotel at the Terrace Bridge Level. Hotel turn around will be maintained concrete pump and concrete trucks will be on the west side of World Trade Ave. Police detail will be controlling traffic.

Terrace Bridge – slab edge waterproofing is underway, and will result in periodic lane closure with a police detail while it is being completed

Fire Alarm Testing – ongoing device testing underway, with horns and strobes initiated periodically on Monday – Saturday from 7AM – 3.30PM through the next two weeks

Landscape and hardscape of sidewalk along the west bound side of Seaport Boulevard

Planter Landscape and hardscape on World Trade Avenue from the Hotel turn-around to Seaport Boulevard bridge

Terrace Bridge sidewalk prep for canopy installation

Interior Finishes on-going for drywall, doors and reclaim wood painting

Planter landscape and hardscape in the plaza

Façade GFRC install on east & west apron

Exterior Envelope activities continue on the roof and exterior elevations working north to south during daytime